Glossary · Regulations and registration
Key points
- In England, a new circuit, a consumer unit replacement and any change to circuits near a bath or shower are notifiable under Part P.
- A registered competent person self-certifies the work. Otherwise a third-party certifier or the local building control body must be used.
- The installer or their scheme must give the certificate to the occupier and to building control within 30 days of completion.
- It is a different document from the Electrical Installation Certificate, which is the BS 7671 safety paperwork.
- Without the certificate, you may struggle to prove compliance when you sell, and the person doing the work can be prosecuted and fined.
How the certificate works
Some electrical work in a home has to be notified to building control. Approved Document P, the statutory guidance for England, says that work is notifiable if it is the installation of a new circuit, the replacement of a consumer unit, or any addition or alteration to existing circuits in a special location, which means the space around a bath or shower. Other additions and alterations outside those locations, and replacements, repairs and maintenance anywhere, are not notifiable.[1]Ministry of Housing, Communities and Local Government, Electrical safety: Approved Document P (2013 edition)
For notifiable work, one of three routes must be used to show it complies with the Building Regulations.[1]Ministry of Housing, Communities and Local Government, Electrical safety: Approved Document P (2013 edition)
| Route | Who | What you receive |
|---|---|---|
| Self-certification | An installer registered with an authorised competent person scheme | A Building Regulations compliance certificate |
| Third-party certification | A registered third-party certifier appointed before work starts | A compliance certificate from the certifier’s registration body |
| Building control | The local authority or a private approved inspector, notified before work begins | A completion certificate, or a final certificate from an approved inspector |
The building control notification route is the one for an installer who is not registered. They must notify a building control body before the work begins.[1]Ministry of Housing, Communities and Local Government, Electrical safety: Approved Document P (2013 edition)
The 30-day rule
Electricians who are registered competent persons complete a BS 7671 installation certificate for every job, and give it to the person who ordered the work. The installer or their registration body must then, within 30 days of the work being completed, give a copy of the Building Regulations compliance certificate to the occupier and give the certificate, or its information, to the building control body.[1]Ministry of Housing, Communities and Local Government, Electrical safety: Approved Document P (2013 edition) In rented homes the certificate may go to the person who ordered the work and be copied to the occupier.[1]Ministry of Housing, Communities and Local Government, Electrical safety: Approved Document P (2013 edition)
For electrical work in dwellings, the GOV.UK list of authorised competent person schemes names BESCA, Blue Flame Certification, Certsure (NICEIC), NAPIT and OFTEC. Anyone joining an electrical scheme is included in a single electrical competent person register for householders to find registered electricians.[3]Ministry of Housing, Communities and Local Government, Competent person scheme: current schemes and how schemes are authorised Our page on NICEIC vs NAPIT compares the two best known. Martin Day Electricians is an NICEIC Approved Contractor and Part P registered, and tells customers that work is notified where the regulations require it.[5]Martin Day Electricians, Electrician in Leeds
Example
Ravi has his old fuse box replaced with a new consumer unit in his house in Oakwood. Replacing a consumer unit is notifiable.[1]Ministry of Housing, Communities and Local Government, Electrical safety: Approved Document P (2013 edition) His electrician is registered with a competent person scheme, so they self-certify. Ravi receives an Electrical Installation Certificate, which is the BS 7671 safety record. The compliance certificate follows from the scheme within 30 days. Ravi files both together. Our page on the electrical installation certificate covers the first document, and when to replace a consumer unit covers the job.
What people get wrong
People often think the Electrical Installation Certificate and the Building Regulations compliance certificate are the same piece of paper. They are not. The first records that the work met BS 7671 and goes to whoever ordered it. The second confirms compliance with the Building Regulations, and a copy goes to building control as well as the occupier.
The second mistake is going without. GOV.UK says the person doing the work could be prosecuted and fined if they do not comply, the building control body could make you pay to fix faulty work, and without approval you will not have the certificates of compliance you may need when you sell your home.[2]GOV.UK, Building regulations approval If an installer will not provide a certificate, Electrical Safety First says to contact their certification body if they are registered, or building control if they are not, because the duty to notify then falls on the consumer.[4]Electrical Safety First, FAQ for Electrical Safety - Your Questions Answered
The bottom line
Notifiable electrical work needs sign-off under Part P. A registered electrician provides it by self-certification and sends the compliance certificate to you and to building control within 30 days. It is separate from the Electrical Installation Certificate, and you should keep both. If you are unsure whether a job is notifiable, ask before the work starts. Our article on NICEIC and Part P qualifications explains what the registration means.
Common questions
What electrical work needs Building Regulations approval?
In England, Approved Document P says notifiable work is installing a new circuit, replacing a consumer unit, and any addition or alteration to existing circuits in a special location such as around a bath or shower.
Who issues the certificate?
An installer registered with an authorised competent person scheme issues it after notifiable work. If they are not registered, a registered third-party certifier or the local building control body certifies the work instead.
How long does the certificate take to arrive?
The installer or their registration body must give a copy to the occupier and to building control within 30 days of the work being completed.
What if the electrician did not give me a certificate?
Electrical Safety First says to ask for one. If the installer is registered and will not provide it, contact their certification body. If they are not registered, contact building control.
Sources
We cite the original source for every fact: legislation, GOV.UK, HSE, the IET, registration bodies and manufacturers' own documents. Each one shows the date we last checked it.
- Ministry of Housing, Communities and Local Government. Electrical safety: Approved Document P (2013 edition). Checked 11 November 2026. ↩
- GOV.UK. Building regulations approval. Checked 11 November 2026. ↩
- Ministry of Housing, Communities and Local Government. Competent person scheme: current schemes and how schemes are authorised. Checked 11 November 2026. ↩
- Electrical Safety First. FAQ for Electrical Safety - Your Questions Answered. Checked 11 November 2026. ↩
- Martin Day Electricians. Electrician in Leeds. Checked 11 November 2026. ↩
Where this matters
NICEIC and Part P qualifications explained